Weight

David BladesMember for 22 years 6 months
Created
3
1
0
I have a tender request that I am dealing with just now and part of the planning section contains a request that I am not entirely sure of the best way to handle it.
The project is made up mainly of engineering and each section will contain 4 revisions the client wants the breakdown as follows - issue rev 1 60%, issue rev 2 10%, issue rev 3 10% and issue rev 4 20%. Of course with the 4 tasks under each wbs section as rev 1 completes and shows 100% it feeds up showing 25% complete of the entire task.
Is there anyway to roll up taking into account the weights mentioned?

Thanks in advance
David

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Hi David,

    Is your Program cost loaded? If it is just spread the cost to each 4 activities with that weightings and P6 will calculate base on the weighting you allocated.
    Alternatively if you don’t want to affect the cost you can use this method.

    Under Project Window-> Calculation tab-> Default Price/Unit for Activities without resource or role Price/Unit enter $1 or $0.01 (less value much better so cost will show as zero rounding but actually it will record up to the last digits in the background)
    Under Activity Window-> Status tab change labor unit to labor cost and enter the weightings as per sample below.
    Rev1 = $0.06
    Rev2 = $0.01
    Rev3 = $0.01
    Rev4 = $0.02
    or Use Top Down Estimate
    If you need more understanding click link below as it was explain further to this forum.
    Weightings Post #2
  2. 0
    David Blades ·
    Rodel, Thank you.
  3. 0
    Rodel Marasigan ·
    Your Welcome David,
    I’m happy to help.