Resource loading report
In the Open Standard
Alaa Al hajMember for 18 years 11 months
- Created
- 2
- 2
0
hi every body
how can i cretae resource laoding report and get only the summary for WBS level i decide say level 4
when i tray i get detailed resource like below
example let us say my project is divided into 2 units
unit 1
unit 2
Project
unit 1 -wbs
activity 1 resource 1 (labor)
R 2 welder
Activity 2 R2 welder
R3 Pipe fitter
Activity 3 R1 labor
R4 Rigger
UNit 2 - WBS
Activity 4 R2 welder
Activity 5 R1 labor
R2 Welder
R4 Rigger
is it possible to get report from primavera like below
unit 1 Day1 D2 D3 D4 ..........
R1 1 3 2 for all activities under this WBS
R2
R3 0 4 5
R4
Unit 2 D1 D2 D3 D4 .........
R1 0 2 1 for all activities under this WBS
R2 3 4
R3 4 5
regards
Alaa
R4
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?
