Resource loading report

Alaa Al hajMember for 18 years 11 months
Created
2
2
0

hi every body
how can i cretae resource laoding report and get only the summary for WBS level i decide say level 4
when i tray i get detailed resource like below
example let us say my project is divided into 2 units
unit 1
unit 2

Project
unit 1 -wbs
activity 1 resource 1 (labor)
R 2 welder

Activity 2 R2 welder
R3 Pipe fitter

Activity 3 R1 labor
R4 Rigger

UNit 2 - WBS
Activity 4 R2 welder
Activity 5 R1 labor
R2 Welder
R4 Rigger

is it possible to get report from primavera like below
unit 1 Day1 D2 D3 D4 ..........
R1 1 3 2 for all activities under this WBS
R2
R3 0 4 5
R4

Unit 2 D1 D2 D3 D4 .........
R1 0 2 1 for all activities under this WBS
R2 3 4
R3 4 5

regards
Alaa
R4

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Alaa,
    Use Resource Assignment Window and Group & Sort by WBS 4, Resource Name and tick Summary only as shown on sample below.
    WBS 4 RL
  2. 0
    Alaa Al haj ·
    Thanks Rodel
    really appreciated
    it is very good idea - correct result and very easy to use

    thanks again
    yours
    Alaa

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?