Why does resource limit line varies

Haresh JayanthMember for 20 years 1 month
Created
1
4
0
I have set a resource limit as Max/ Unit 1. But when i see this resource limit in resource profile, it shows fluctions (Zigzag line) and not a Straight line eventhough i have only set one max/unit to the resources .

How can it shows Zigzag limit line , if i set one max/ unit to that resource...

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    If your calendar working hours is 8hr mon-fri and 4hrs sat plus other non working period like holiday make your limit as zizag.
    Change your timescale to day/hour so you can understand your resource limit.