Changing Activity ID inbetween using Global Change
In the Open Standard
Haresh JayanthMember for 20 years 1 month
- Created
- 2
- 2
0
Suppose i have around 50 activities with activity ID SUTSGF001,SUTSGF002....and so on.....
I want to change all activities in that WBS to SUTSFF001, SUTSFF002....and so on..i.e to replace "GF" to "FF" in the middle using Global change.......What is condition i have to apply....
I want to change all activities in that WBS to SUTSFF001, SUTSFF002....and so on..i.e to replace "GF" to "FF" in the middle using Global change.......What is condition i have to apply....
2 replies
Oldest firstLog in or join to reply