importing an XER file with EPS activity codes
In the Open Standard
vito Kooij, vanMember for 20 years 10 months
- Created
- 8
- 3
0
Dear Members,
I have a P6.2, and the next problem.
I have a project with EPS activity codes.
I have a client who wants XER file. If he imports into his own database, then the EPS activity codes do not come along.
I also tried the XML file, but the EPS activity codes are not put in EPS structure where the project stands.
Is there a hidden setting that allows for an XER file to import all data from the project (including the EPS activity codes)
PS. in the export file, the codes are available!
thanks for your comment
I have a P6.2, and the next problem.
I have a project with EPS activity codes.
I have a client who wants XER file. If he imports into his own database, then the EPS activity codes do not come along.
I also tried the XML file, but the EPS activity codes are not put in EPS structure where the project stands.
Is there a hidden setting that allows for an XER file to import all data from the project (including the EPS activity codes)
PS. in the export file, the codes are available!
thanks for your comment
8 replies
Oldest firstLog in or join to reply