Skip to content

Resource Units

Jeffrey NewmanMember for 21 years 2 months
Created
1
2
0
Can anyone help me?

I have resourced a schedule but when I go to check total units there is a difference in units dramatically in the Activity usage spreadsheet remaining units and the resource assignments remaining units. Both don’t tally overall and on wbs breakdown sections of work.

I thought both sheets are supposed to tally?

HELP! where am I going wrong......

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Jeffrey,
    It should be the same except if you define some of them are not using resources and used status tab-> labor units Or expenses tabs.
    If using only resources units then the only reason why it has difference is on Resource Assignment Window maybe filtered. Check the filter and remove if any and you should have same remaining units for both activity usage spreadsheet and resource assignments.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?