Original Duration
In the Open Standard
Rizwan Rauf, PMPMember for 17 years 3 months
- Created
- 1
- 1
0
Dear All,
I am just confused about Original Duration in Primavera. For example, if I put OD of 7 days in an activity and that activity was completed intermittently in one month, so should I change the OD according to Actual Start/Finish.
Moreover, If I fix Original Duration and after sometime, I came to know that this duration is not correct, So its logical to change it or not?
Thanks & Best Regards,
Rizwan Rauf
I am just confused about Original Duration in Primavera. For example, if I put OD of 7 days in an activity and that activity was completed intermittently in one month, so should I change the OD according to Actual Start/Finish.
Moreover, If I fix Original Duration and after sometime, I came to know that this duration is not correct, So its logical to change it or not?
Thanks & Best Regards,
Rizwan Rauf
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?