How to send a copy as target baseline

Haresh JayanthMember for 20 years 1 month
Created
1
2
0
Hi,

When we export a project , the assigned baseline is not exported along with the project......So how to send a program to different user with the assigned baseline program intact???? Is it possible.......

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Haresh,
    You need to detach the baseline and restore then export together with current project and will create only one xer then if emailed to someone inform the recipient to attach the baseline after importing.