Edit, User Preferences, Resource Analysis

Haresh JayanthMember for 20 years 1 month
Created
2
1
0
In Edit , user preferences , resource analysis tab,

what is the meaning of the function

"When all Projects are shown in the resource usage profile and spreadsheet, all opened projects are included as well as the closed projects specified below"

However if i select the tab " Opened Project only" then why does all resources used in all the projects are displayed...

I want to display only resources of my "open projects only" is it possible....

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Haresh,
    It will show depends on the settings that you selected. If you look closely on the right panel window only open project will have equivalent value even all resources are shown on the left panel window. If wanted only resource for open project whether open project settings is selected or not right click left panel window and select Filter by-> Current Project’s Resources
  2. 0
    Haresh Jayanth ·
    Thanks rodel for your explanation.......

    regards,

    Haresh Jayanth