Confusion between budget....

Irfan KhanMember for 17 years 3 months
Created
1
2
0
Hi to all,

Can anybody tell me that what is the difference between Budget At Completion > At Completion Total Cost & Original Budget.



Thanks,,,


1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Irfan,
    Original Budget is Contract Amount including Overhead, Provisional Sum, Profit, Margin etc...

    Budget At Completion (BAC) = Budget + Approved Variation/Changes use as base to measure Earned Value.
    AT Completion = Actual cost + Remaining cost = Forecast At Completion