Critical Path
In the Open Standard
Kandarp JoshiMember for 16 years 5 months
- Created
- 6
- 2
0
Planners,
Query with reggards to Critical Path in P6.
If I do not link task dependent activity to finished milestones and schedule the project, it does not give me critical path. I suppose P6 gives you critical path as the longest chain of activities in a project and linking to a finish milestone is not a manadatory case.
Also, If I link activities to finsihed milestones & schedule the project, it automatically changes the finished milestone dates. In this case I do get the critical path but original milestone dates do not exist any more.
Anyone can explain how to get over this? Thanks.
Kandarp
Query with reggards to Critical Path in P6.
If I do not link task dependent activity to finished milestones and schedule the project, it does not give me critical path. I suppose P6 gives you critical path as the longest chain of activities in a project and linking to a finish milestone is not a manadatory case.
Also, If I link activities to finsihed milestones & schedule the project, it automatically changes the finished milestone dates. In this case I do get the critical path but original milestone dates do not exist any more.
Anyone can explain how to get over this? Thanks.
Kandarp
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?