Original Duration does not changing after importing MPX
In the Open Standard
Haresh JayanthMember for 20 years 1 month
- Created
- 5
- 4
0
Hi,
I have imported a MS Project program in P6. But i noticed that the orginal duration of the project after importing is not changing , For example a duration is 15 , even if i change to 25 days , the early finish or nothing is affected..this applies to all activities......what is the solution for this type of problem....I have checked all this
a) Constraints
b) Project Window - Calculation tab - reset OD & REM. Units..& also reset remaining duration....
c) Checked all the user preferences tab etc.....
Still the problem presists, can anyone guide me...
regards,
Haresh Jayanth
I have imported a MS Project program in P6. But i noticed that the orginal duration of the project after importing is not changing , For example a duration is 15 , even if i change to 25 days , the early finish or nothing is affected..this applies to all activities......what is the solution for this type of problem....I have checked all this
a) Constraints
b) Project Window - Calculation tab - reset OD & REM. Units..& also reset remaining duration....
c) Checked all the user preferences tab etc.....
Still the problem presists, can anyone guide me...
regards,
Haresh Jayanth
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?