Resource: One Supervisor for the full term of a Project

Ruel CamaquinMember for 17 years 11 months
Created
1
5
0
Guys,

How do i do this, i have foreman for the complete duration of a project, how do i put him in the resources just once? if i put the foreman in every activities that i have, then my resources cost for the foreman shall be overallocated. Kindly give me tips & tricks on how to do this in P6.

Thanks in advanec for your immediated response.

Ruel

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Ruel,
    Use Level Of Effort activity link SS to first activity where the foreman assigned and FF to last activity and assign resource foreman. If will automatically adjust if the last activity move forward or backward.