Budget Units is linked to Duration

Haresh JayanthMember for 20 years 1 month
Created
2
4
0
Dear Rodel,

I have one problem, whenever i change my Budgeted units of any resources then my duration changes.......The activity type is task dependant......Can you guide me.....why resource budgeted units is linked to duration......

regards,

Haresh

2 replies

Oldest first
  1. 0
    Pinan T. ·
    Try to Use Duration type Fixed Duration and Units
  2. 0
    Rodel Marasigan ·
    Haresh,
    The reason why your duration change when budget units is change because you use a duration type "Fixed Units" or "Fixed Unit/Time" and resource "Drive Activity Date" is tick. If you used this duration type settings and don’t want to affect your duration when changing Budget Units then you have to un-tick "Drive Activity Date" under resource assignment on each resource. Alternatively use Fixed Duration and Unit" or "Fixed Duration and Unit/Time". Using this settings will ignore "Drive Activity Date" settings on resource which I already explain to your before when you are querying about P3.x Driving resource equivalent to P6.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?