Store period performence

shaik BarkatullaMember for 16 years 6 months
Created
3
15
0
Dear All,

If i click for store period performence what should be the financial period date? (should be equal to data date???), please clarify.

Regards

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Shaik,
    Using period performance you need to define financial period date first. Your financial period will depend on your progress cut-off. It can be weekly, monthly which can be set by batch. If you are tracking your project weekly and producing s-curve, EV, Activity spread value, resource spread value every month only then financial period should be define as monthly. If producing this type of report weekly then your financial period should be weekly.
  2. 0
    shaik Barkatulla ·
    Dear Rodel,

    Thank you very much,

    If i am updating for this week the data date is coming by default as 29-May-10, then financial period value also to be set as 29-may-01.
  3. 0
    Rodel Marasigan ·
    Shaik,
    If your cut-off weekly is Saturday then create financial period date every Saturday.

Log in or join to reply