Actual Units exceed Data Date
In the Open Standard
Rifky SoedirdjaMember for 16 years 5 months
- Created
- 5
- 2
0
Hi All,
I don’t understand why actual units for some activities in my P6 are exceeding the data date? For example, I put data date on 01-May-10 08.00 to capture the progress for weekending 24-30 April 2010 17.00. But, when I see through resource usage spreadsheet, I can still see some unit manhours on the 1st-May-10. I am expecting to see the total remaining units from 1-May-10 until end of project. Can somebody help? Thanks.
Rgds,
Rifky
I don’t understand why actual units for some activities in my P6 are exceeding the data date? For example, I put data date on 01-May-10 08.00 to capture the progress for weekending 24-30 April 2010 17.00. But, when I see through resource usage spreadsheet, I can still see some unit manhours on the 1st-May-10. I am expecting to see the total remaining units from 1-May-10 until end of project. Can somebody help? Thanks.
Rgds,
Rifky
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?