Filter delayed activities in P6.1
- Created
- 13
- 5
13 replies
Oldest first- 0GWGary Whitehead ·
Note that this filter will
Note that this filter will show activities with an extended duration.
It won't show activities that have started late but retained the same duration.
Instead of variance to duration, I prefer to use variance to finish date.
Also I prefer to set my baseline not to current project, but to a baseline project when checking schedule variance -either the contract baseline, or a copy of the project from previous update period.
- 0SKSanthosh kumar Narayanan ·
hi folksYou can filter the
hi folks
You can filter the delayed activities
Where " BL Start" is "is lessthan" Value "DD"
and "Actual start is "equals" "blank" (Dont ype anything leave just blank
You will get the "activities planned to start but not started" same way you filter " Activiites planned to finish but not finished"
Santhosh
- 0SKSanthosh kumar Narayanan ·
Hi AndersonI have explained
Hi Anderson
I have explained in my comment is self
You can filter the delayed activities
Where " BL Project Start" is "is lessthan" Value "DD"
and "Actual start is "equals" "blank" (Dont ype anything leave just blank
You will get the "activities planned to start but not started" same way you filter " Activiites planned to finish but not finished"
To filter " Activiites planned to finish but not finished
Where " BL Project Finish " is "is lessthan" Value "DD"
and "Actual Finsh is "equals" "blank" (Dont type anything leave just blank)
Santhosh
- 0KDKhuong Do ·
Hi,I write an article
Hi,
I write an article regarding How to quickly identify Behind Schedule and Over Budget activity by Indicator UDF in Primavera P6.
If you're interested, kindly read it here https://doduykhuong.com/2017/03/14/how-to-quickly-identify-behind-schedule-and-over-budget-activity-by-indicator-udf-in-primavera-p6/
- 0ARAbdul Razeed Raja ·
GUYS BEST WAY TO DO IS FILTER
GUYS BEST WAY TO DO IS FILTER SCHEDULE VAIRANCE INDEX-LABOR UNIT LESS THAN ZERO. ITS AVAILABLE INSIDE COLUMN EARNED VALUE .
BY FILTERING SUPPOSE TO START BUT NOT STARTED, SUPPOSE TO FINISH BUT NOT FINISH WILL NOT GIVE STARTED BUT THE PROGRESS IS NOT UPTO THE MARK AND WILL FINISH LATE. ALSO VARIANCE OF BL DURATION WILL ONLY GIVE THOSE ACTIVITIES WHICH TOOK LONGER TO COMPLETE THEN THE PLANNED
- 0PJPhilip James ·
Bit of an old
Bit of an old thread.
However. Can you have filter what was planned to start and didn't and what planned to finish and didn't - in the period on the same filter?
I used the examples below on two separate filters, but of course. If filters activiities that match 'both' -
How do I write the filter to have 'planned start' or 'planned finish'?
Where " BL Start" is "is lessthan" Value "DD"
and "Actual start is "equals" "blank" (Dont ype anything leave just blank
You will get the "activities planned to start but not started" same way you filter " Activiites planned to finish but not finished"
OR
To filter " Activiites planned to finish but not finished
Where " BL Project Finish " is "is lessthan" Value "DD"
and "Actual Finsh is "equals" "blank" (Dont type anything leave just blank)
Regards
Philip
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?