Sorting by activity code

Lucas lMember for 16 years 7 months
Created
2
2
0
Hi,

can i check the procedure to sort by activity code instead of WBS?

I tried the group and sort options but there’s no activity code for sorting

2 replies

Oldest first
  1. 0
    Andrew Dick ·
    Lucas,
    When you create the activity code make sure you give it a unique name. Generally I will prefix mine either with my initials or the project identifier for which it will be used, to make it easy to find and /or provide ownership of the code so other users don’t modify or delete it.

    When you group and sort you search for the codes name in the drop down selection.

    Andy
  2. 0
    Rodel Marasigan ·
    Lucas,
    When defining Activity Codes Planner/User can also organise the sort order/ sort sequence by clicking arrow up and down.
    Another option is on Group & Sort function there is a tick box for sort bands alphabetically.
    Note: Activity code is a text so when using numeric character make sure to use zero first followed by the number:
    Ex: 01, 02, 03…etc…

Log in or join to reply