Resource Assignments

Haresh JayanthMember for 20 years 1 month
Created
1
2
0
Hi,

In Project tab , resource assignments , "When updating Actual units or cost" what is the meaning of:

"Add actual to remaining"
"Subtract actual from at completion" ......

can anyone explain....

regards,

Haresh Jayanth

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Haresh,
    It’s so simple, if Add actual to remaining is tick then what ever the remaining is, actual will be added to remaining and at completion will be more than budget.
    Formula: Budget = At completion = Remaining (i.e. 10 = 10 =1 0 no progress)
         Actual + Remaining = At completion (i.e. 5 + 10 = 15 with Progress)
    If Subtract Actual from At Completion is selected then if Budget = At Completion = Remaining at no progress then when progress, At Completion – Actual = Remaining (i.e. 10 – 5 = 5) therefore At Completion = Budget

Log in or join to reply