Resource Profile Histogram in a report

Tim BreedingMember for 17 years 6 months
Created
1
14
0
Does anyone know how to get a report that displays the resource usage profile histogram?

I’m trying to post some resource histograms automatically to the web via job services.

Anyone know?

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Tim,
    Unfortunately there is no option to produce resource histogram and resource usage profile using report. I used Publish-> Tracking layout function instead to publish it to web. You can create resource histogram layout in Tracking module and select this layout on Publish function but still not available on Job Services functions.