Recent upgrade to Primavera 6.7 SP1 – huge SQL transact
In the Open Standard
Stuart FairweatherMember for 16 years 6 months
- Created
- 1
- 3
0
We’ve recently upgraded from Primavera 5.0 SP7 to 6.7 SP1 and we’re having major issues with the database transaction log (we’re using SQL Server 2005 running in 2000 compatibility mode). If we truncate the log it remains small for a few hours then starts to grow and within the space of a day it fills the server hard drive – 13GB in our case. Has anyone had similar problems? We didn’t have this problem when we were on P5 and no hardware or DB configurations have changed. The SYMON job appears to be running every minute as it should and we’ve scheduled DAMON to run daily (default 1 week).
Cheers
Cheers
1 reply