Skip to content

Importing from P6 to MSP....Activity Codes Issue

Mohsen MMember for 18 years 7 months
Created
1
3
0
Hi All,

I’m having trouble with exporting a P6 file to MSP. The P6 file has Activity Codes assigned but when I export the file to MSP, the Activity Codes won’t come over. So I can’t see the same layout as I see in P6. Any idea how can I get the same layout as fast as possible?

Thanks
M

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Mohsen,
    Global & EPS level activity codes are not exported to MSP only Project level activity codes. If you define Project level activity codes it will automatically converted to Task Outline Code in MSP same as Resouce Code = Resource Outline Code.

    Note: UDF codes requires mapping in order to export to MSP.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?