1 day activity with calendar problem
In the Open Standard
Glenn Dexter UbaldoMember for 17 years 4 months
- Created
- 7
- 2
0
Hello Guys,
I have 1 day activity duration in my programme but when i look at the dates it is showing a date of for 2 days for example.
expected outcome
duration start finish
box fixing 1 day june 1 8:00 am june 1 6:00 pm
but results to :
duration start finish
box fixing 1 day june 1 8:01 am june 2 8:01
I already assign a 10 hour per day calendar but the result is the same. any ideas guys on how to solve this.
thanks in advance,
Glenn
I have 1 day activity duration in my programme but when i look at the dates it is showing a date of for 2 days for example.
expected outcome
duration start finish
box fixing 1 day june 1 8:00 am june 1 6:00 pm
but results to :
duration start finish
box fixing 1 day june 1 8:01 am june 2 8:01
I already assign a 10 hour per day calendar but the result is the same. any ideas guys on how to solve this.
thanks in advance,
Glenn
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?