1 day activity with calendar problem

Glenn Dexter UbaldoMember for 17 years 4 months
Created
7
2
0
Hello Guys,

I have 1 day activity duration in my programme but when i look at the dates it is showing a date of for 2 days for example.

expected outcome
duration start finish
box fixing 1 day june 1 8:00 am june 1 6:00 pm

but results to :
duration start finish
box fixing 1 day june 1 8:01 am june 2 8:01

I already assign a 10 hour per day calendar but the result is the same. any ideas guys on how to solve this.

thanks in advance,
Glenn

7 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Glenn,
    Check the predecessor finish date it may be the cause to start at 8:01 AM. Also show the Duration decimal and it may not whole number.
  2. 0
    Glenn Dexter Ubaldo ·
    Hello Rodel,

    Thanks for the fast reply, I checked already but it still
    showing that the activity with the 1 day duration starts
    at 8:01 and ends with 8:01 of the following day meaning to
    say it is showing that this activity duration for 2 days, I
    also try 1 activity with no links and with 1 day duration but still showing the same pattern.

    Is there any option which I can set that the start of every activity should be 8:00 am and the finish should
    be 6:00 pm.

    thanks,
    Glenn
  3. 0
    Rodel Marasigan ·
    Glenn,
    What is your data date time? Can you also check the Hours time period if set to 10 hrs.
  4. 0
    Evaristus Ujam ·
    Glenn,

    There are possibly two reasons for this abberation:
    1 Your system is formated to recognise a 12hr calender day for 24hr calender day. In which case a 24hr calender activity is reported by the software as 2days.

    2 You have a constraint somewhere in your programme that tells the your program to delay for one day before starting.

    In either case this anomaly is not unexpected.
    Please check out for these anomalies and be sure they do not exist
    Regards
    Ujam
  5. 0
    Sandy Matheson ·
    When I started using P6 a few years ago I identified thia problem. Primavera helpline/site advise that this is correct as per ’specification’, 1 day activity starts 00.01 and finishes next day at 00.01. This has caused us continual problems as when you present this to ’non-planners’ who see 1 day activity start on a date and finish on following date they intuitively read this as 2 days. Explanation that "this is how P6 does it" is often met with response "well it is not correct, fix it!". So you end up bodging the durations or using a user field to hold a corrected finish date - the old ’work arounds’. Crap really.
  6. 0
    Rodel Marasigan ·
    Hi Sandy,
    It is the first time I heard that and I haven’t read any P6 books or reference having that specifications. Can you elaborate your claim? Are you still having that issue?

    Best Regards,
    Rodel
  7. 0
    Rafael Davila ·
    Glen:

    Believe you got it right in your posting no 3.

    “Is there any option which I can set that the start of every activity should be 8:00 am and the finish should be 6:00 pm.”

    Try entering activity duration in days instead of hours, if it spans a single work day you nailed it, it is an issue of workday duration defined slightly less than 8 hours.

    I do not have P6 so my recommendations will follow instinct. Try moving to Calendar definition, look for the assigned week definition for your activity calendar and perhaps here you will be able to edit work hours or start and finish of your workday. All software has its own methods to deal with calendar, work week and work hours but I do not believe there is a miss by P6 here.

    Best Regards,
    Rafael

Log in or join to reply