Activity type Selection
In the Open Standard
Kumar SMember for 16 years 8 months
- Created
- 1
- 2
0
dear Guys,
Can any body suggest me which activity type can be used for the following activities.
i have scaffolding erection and insulation removal as two activites which are starting before the shutdown and has to be finihed by the time shutdown starts.
so which type of activity i can assign for this activities.
i am not assighning any resuorces for this jobs.
so the activities are not considered during levelling also..
Please guide me..
1 reply