Skip to content

Activity type Selection

Kumar SMember for 16 years 8 months
Created
1
2
0
dear Guys, Can any body suggest me which activity type can be used for the following activities. i have scaffolding erection and insulation removal as two activites which are starting before the shutdown and has to be finihed by the time shutdown starts. so which type of activity i can assign for this activities. i am not assighning any resuorces for this jobs. so the activities are not considered during levelling also.. Please guide me..

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Kumar,
    You can use Task Dependent for both running parallel and a successor of Shutdown activities.

    Ex:
    Scaffolding erection -> FS -> Shutdown
    Insulation removal -> FS -> Shutdown

    If the Insulation crews required scaffold to remove insulation then -> Scaffolding erection-> FS ->Insulation Removal-> FS->Shutdown

    If Insulation crews can start from the area where scaffolding are finished and continue to erect scaffold on other area where insulator crew is not required then -> Scaffolding erection -> SS + say 5 days lag Insulation removal-> FS -> Shutdown, Scaffolding erection -> FS -> Shutdown

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?