MAX UNITS/TIME

Kumar SMember for 16 years 8 months
Created
6
3
0
Dear,
can you please clear my doubt regarding the MAX UNITS/TIME for the resources.
for the pipe fitter the value is 60h/h.
for helper it is 10h/h.
what does it mean.
please explain me this.

thanks in advance...

6 replies

Oldest first
  1. 0
    Pinan T. ·
    are you using P6 v 7.0?

    i think its a bug resolved in SP1
  2. 0
    Rodel Marasigan ·
    Kumar,
    Max Unit/Time is the max limit of unit that allocated on the resource per time when assigned resource to activity. Exceeding from the set max unit/time will over allocate your resource and prevent Primavera from leveling the resource. Max unit/time can set to individual resource (single person) or group resource (gang or crew).

    Ex: If normal working time is 10 hrs per day meaning 1 person = 10hrs/day
    If a resource is a single person max unit/time = 10 max unit/time
    If a resource is a crew/ group or gang of 5 person = 10 x 5 = 50hrs/d = 50 max unit/time
  3. 0
    Kumar S ·
    thank you very much for your quick reply sir..

  4. 0
    Sajith Raj ·

    Hi,    I am having trouble

    Hi,

        I am having trouble while importing a modified max unit/time back to P6, it doesn't update to changed values. When I export as per othe planners advise I have exported Resource & Resource assignement. Then changed few values of max unit/time and it didn't change after importing back. Any help in this case.

     

    Thanks 
    Raj

  5. 0
    Zoltan Palffy ·

    Kumarits usually X number/day

    Kumar

    its usually X number/day or X number/hour whatever your planning unit is

    its not 60h/h or 10h/h that would be 60 hours per hour or 10 hours per hour.

    if setting the Max Units /Time the 60/d would mean that the resoruce could work 60 hours per day or would be a crew of 7.5 men which is 60 hours/8 hours per day. The crew size would change if the work hours were lets say 10 hours per day it woule be a crew of 6 men becasue 60 hours /10 per days  = 6 men.

    Rodel explained what setting a max limit does 

     

  6. 0
    Zoltan Palffy ·

    Sajithtry addding the

    Sajith

    try addding the resource again because the resource keeps the rules that were established at the time that the resource was assigned to the activity. 