P6 - calculate rem. units based on Activity % comp.

Abhijeet RanadhirMember for 20 years 3 months
Created
1
2
0
I need help to calculate remaining Units on resources in P6 based on the activity % complete. I want to physically update % comp and accordingly want to cacluate the reaource actual and remaining based on the physical % comp. Will I be able to do this?

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Abhijeet Ranadhir,
    If your duration type is either Fixed Duration & Units or Fixed Duration & Unit/Time and Percent Complete type is Duration % then updating % complete will automatically update Actual & Remaining duration (synchronise update). If you are using Physical % for Percent Complete type then everything is manual input.