Skip to content

Some activities bar color not seen in Gantt chart??

Luis GonzalesMember for 18 years
Created
3
1
0
hallo every one..

I am new user of P6..can anyone here help me how to solve my problem..my problem is some remaining works activities bar color(Green) on the gantt chart are not reflected/seen? but most of the activities are seen?


thanks in advance...

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Luis,

    WELCOME TO PLANNING PLANNET!!!

    Is it a timescale problem or zero duration left but not completed?
    If timescale problem then change the timescale from ??? (i.e. year/months) to week/day
    Right click on Gantt chart area and select time scale then change Date interval to Week/Day
  2. 0
    Luis Gonzales ·
    Thanks sir Rodel,

    I’ve change already the time scale to week/day,but still not seen the bar color(green/remaining work)on the gantt chart for that particular activities..the only color reflected on that activities are the baseline(yellow) and the Actual works(blue)..
    sir if its okay with you,can I email to you the file so that you can view it..I tried to attach here the spot view of that activities with the gantt chart but I dont know how to do it..

    thanks

    Luis
  3. 0
    Faheem Faiz ·

    HOW TO CHANGE THE COLOR OF

    HOW TO CHANGE THE COLOR OF STANDARD NONWORK EXCEPTION IN CALENDAR IN PRIMAVERA P6

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?