Remaining float in P6

Shah. HBMember for 17 years 10 months
Created
4
2
0
Hi to all

What is remaining float ? How it is computed?

4 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Shahul,
    My understanding with remaining float is the same as total float and they computed the same. Once the activity is in progress the remaining early date = early date and when finished or completed remaining early date = null and early date = data date.
  2. 0
    Shah. HB ·
    Many Thanks Rodel
  3. 0
    Ronald Winter ·
    I co-published a paper titled, "Understanding P6 Dates" that explains Remaining Float. The secret is that Remaining Float is different from Total Flaot is you are using resource leveling. I hope that this helps!
  4. 0
    Shah. HB ·
    Many thanks for sharing your article Mr.Ronald