Importing .mpp

Naveen SubbaiahMember for 21 years 9 months
Created
4
1
0
Hi,

I am using P5 & while trying to import a microsfot project (.mpp), I am getting the following error. Can anyone help?

"Cannot Save Project. Microsoft Office Project does not support saving projects into ODBC, MPD or MDB formats. Please save the file in a format that is supported by project"

Thanks & Regards
Naveen

4 replies

Oldest first
  1. 0
    Oliver Melling ·
    You need to have MSP on the same machine as P5 in order to import the .mpp files.

    Check you have.
  2. 0
    Naveen Subbaiah ·
    I have it.
  3. 0
    Rodel Marasigan ·
    Naveen,
    P5 only support MS Project 2003 below. If you have MS Project 2007 then you will not be able to import MPP.
  4. 0
    Shah. HB ·
    Hi

    Open your MS Project and save the file as XML format .While importing in P6 use Microsoft Project option and select XML Mode of importing