How can i setting timescale gantt to be see number of the day of the week and not the name of the day of the week...Thanks

4 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Conrad,
    Right click on Gantt Chart area and select Timescale.
    Tick Show Ordinal date and select the date interval you want to use and change the Start date to match number value you wanted to show. If you wanted to show both click Three Lines and you can select both.
  2. 0
    Conrad Cannella ·
    Thanks for the timely rispost.Molto bright as ever. But maybe I explained bad. I wanted to display the corresponding number of weekday and not a progressive. For example, in the year 2010 the first level, second level the months and third level the number of days of that from day 1 to day 30, one month from day 1 to 31, etc. ...
    Thanks a lot
  3. 0
    Rodel Marasigan ·
    Conrad,
    The only setting on Timescale that show day date is using Three line and select Day Shift as Date interval. The last line will be showing 0 if no nightshift calendar used.
  4. 0
    Conrad Cannella ·
    Thanks a lot!