Relationship query...
In the Open Standard
Kumar SMember for 16 years 8 months
- Created
- 1
- 2
0
Plese some body reply to my query........it was a urgent need for my under standing of the project...
Dear guys,
i was refering to the last years project. in the primary baseline bar plan.but there are some relationships which i cannot understand.
for ex i have A and B activities which has FS relationship between them.
there is no lag.
the A activity has FS to some other activity also C .
BUT IN THE SCHEDULE THE B activity is starting before the A activity has finished.
why is this happening.
please clear my doubt.....
thanx...
Dear guys,
i was refering to the last years project. in the primary baseline bar plan.but there are some relationships which i cannot understand.
for ex i have A and B activities which has FS relationship between them.
there is no lag.
the A activity has FS to some other activity also C .
BUT IN THE SCHEDULE THE B activity is starting before the A activity has finished.
why is this happening.
please clear my doubt.....
thanx...
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?