max units / time for the resources
In the Open Standard
Kumar SMember for 16 years 8 months
- Created
- 1
- 2
0
Dear Guys,
please guide me.
i have assigned the resources of the prevoius project for the present project.
since the max units/time were assigned in for the last project.
now if i change the max units then it is getting changed for the last project also.
since resources are enterprise level data,is there any way to assign the new units for the same resource without disturbing the allaocated max units/time for the last project....
thanx,,
please guide me.
i have assigned the resources of the prevoius project for the present project.
since the max units/time were assigned in for the last project.
now if i change the max units then it is getting changed for the last project also.
since resources are enterprise level data,is there any way to assign the new units for the same resource without disturbing the allaocated max units/time for the last project....
thanx,,
1 reply
Oldest firstLog in or join to reply