MSP TO P6 NOT IMPORTING

Kumar SMember for 16 years 8 months
Created
1
3
0
Dear Guys,

i have a microsoft project file (2010.MPP) file.
when i am trying to import it in the P6 there are only 2 file ext types in p3 section that is .xml and .mpx.
so there is no .mpp extension.
so how to open this file guys...

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Kumar,
    You need to have MS Project installed on the same machine in order to import MSP. Who ever gave you MSProject (2010) ask him to save it as xml file so you import it to P6.

    Note: P6 support only MSProject 2003 otherwise it will produce some error even manage to convert but majority failed.