Spilit resource & Budgeted Units using Global change
In the Open Standard
Haresh JayanthMember for 20 years 1 month
- Created
- 1
- 2
0
Hi Rodel,
i have assigned only one type of resources to all activities called "Manpower".
Now my Engineer is instructing to split these resources into two separate resources i.e. 60% of resources to be assigned as skilled workers and 40% of resources to be assigned as unskilled workers.
For example , By the above split all the Budgeted units assigned for all activities by using "Manpower resources" if it has 100 Budgeted units should now read as Skilled workers Budgeted units "60" and unskilled workers Budgeted units "40" . This split should be assigned to all activities.
Is it possible to split these resources and their units for assigned resources by using Global change
regards,
Haresh Jayanth
i have assigned only one type of resources to all activities called "Manpower".
Now my Engineer is instructing to split these resources into two separate resources i.e. 60% of resources to be assigned as skilled workers and 40% of resources to be assigned as unskilled workers.
For example , By the above split all the Budgeted units assigned for all activities by using "Manpower resources" if it has 100 Budgeted units should now read as Skilled workers Budgeted units "60" and unskilled workers Budgeted units "40" . This split should be assigned to all activities.
Is it possible to split these resources and their units for assigned resources by using Global change
regards,
Haresh Jayanth
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?