Primavera version 6.7

Tasnim YusoffMember for 16 years 3 months
Created
3
2
0
Hi,

I have problem regarding duration with my primavera v6.7.
I export files from Primavera v6.2.1 to Primavera v6.7 but the original duration incresed but the start and finish date is still da same date. I checked the calendar and admin preference, it the same setting as my P6.2.1 setting. The original duration for all of da files that i export to P6.7 changed.

Can someone help me regarding this issue?

3 replies

Oldest first
  1. 0
    Andrew Dick ·
    Tasnim,
    Check each calendar you have assigned to the activities in the schedule. The units/time are now set at the calendar level. If this is out of sync with what you had used originally then you may have an issue.

    Also I’m not sure how the WBS durations are calculated if you have different calendars assigned under the same WBS, possibly defaults back to the admin preference for that calculation???

    Andy
  2. 0
    Rodel Marasigan ·
    Tasnim,
    Duration is calculated based on activity caledar assigned as limitation of working period for date and Hours per time period for time unit set (i.e. 8h/d, 40h/w, 173.3h/m etc...)
    check if Hour per Time Period is the same as calendar total working period per day and the same setting on P6.2.1
  3. 0
    Tasnim Yusoff ·
    Hi,

    Thank you. It solved now :)