How to load cost

Gokulakrishnan GanesanMember for 16 years 4 months
Created
4
2
0
Hi.. i’m new to P6.. Can any one tell me how to load cost in P6 easily.. In p3 i will create a resource called BOQ and i’ll add this resource to all activities.. then i’ll load the cost as per the break down in the budgeted cost for this new resource.. but in P6 i have just started trying to load the cost..

4 replies

Oldest first
  1. 0
    Anbin Ponnith ·
    Hai Gokul
    Try the Following Step if u Want to Type Budget Cost Directly
    1.Select Enterprise->Resource Dictionary
    2.Resource Id Type BOQ
    3.Resource Name (XXXXXX)
    3.Resource Type As Material
    4.Click ActivityDetail Tab->ResourceTab->Add Resource->Select BOQ(Resource Id)
    5.Click Status Tab->Right Corner u Can See Labour unit->Change to Material Cost -> Budget Cost ->type the Cost Directly
    Regards
    Anbin
  2. 0
    Anbin Ponnith ·
    Hai Gokul
    In the Resource Dictonary Please Check the Following Option
    1.Select the Resource
    1.Units & Price tab- >Price/unit->1.00 (it May be Zero)
    2.Details->uncheck the calculate cost from unit
    Recalulate Assignment Cost is Calculated base on Price/Unit*Budget Unit
    3.Now if u run Recalculate Assignment Cost I hope it wont Change

    Regards
    Anbin
  3. 0
    Gokulakrishnan Ganesan ·
    Thanks Mr.Anbin.. I have used it.. but still i have some confusion that after entering the budgeted cost like as u told & i clicked the recalculate assigned costs in Tools. Then all of a sudden all the budgeted costs i have enterd is changing.. why is it so?..
  4. 0
    Anbin Ponnith ·
    Hai Gokul
    In the Resource Dictonary Please Check the Following Option
    1.Select the Resource
    1.Units & Price tab- >Price/unit->1.00 (it May be Zero)
    2.Details->uncheck the calculate cost from unit
    Because in P6 if u assigned a resource it will default assigned a budget unit of (8*orginal duration)
    If u run Recalculate Assignment Cost Ur Budget cost will become (Budget unit*Price/unit)
    U need to uncheck the calculate cost from units
    Recalulate Assignment Cost is Calculated base on Price/Unit*Budget Unit
    3.Now if u run Recalculate Assignment Cost I hope it wont Change
    4.U need to uncheck the calculate cost from unit for all the resource u have assigned to the project

    Regards
    Anbin

Log in or join to reply