Resource Profile

Athar HashmiMember for 17 years 6 months
Created
3
3
0
Hey Guys,
I have some problem in resource profiling. in the programme all activites are resources loaded but when i choose ’view-show on bottom-resource usage profile’ then the profile appears only for the resources of one activity. profile is not showing all resources of other activites.
please help.

3 replies

Oldest first
  1. 0
    Anbin Ponnith ·
    Hi Athar
    I Hope in Resource Profile Option It will Appear for the Selected resource and not for selected activity
    If u Want to Display For All Resource
    Click Display->Filter by Curent Project Resource->Ctrl+A Select All the Resource)
    Now it will Display for All Resource
    Regards
    Anbin
  2. 0
    Anbin Ponnith ·
    Hi Athar
    If u Are Using Activity Usage Profile option
    Click Show usage for -> All Activities

    Regards
    Anbin

  3. 0
    Athar Hashmi ·
    Thanx Anbin,
    it’s working, thank you very much