Completed activities in past filter

Morne BeeslaarMember for 17 years 2 months
Created
2
0
Hi all,

I am trying to build a filter which will show me completed activities for the past 2 weeks in P6.7


I tried using Finish within range of ’DD’ DD-2W’ and activity satus = complete

I also tried varying this with actual finish in the same parameters but without luck.

Any suggestions would be most welcome.

2 replies

Oldest first
  1. 0
    Andrew Dick ·
    Morne,
    You have the equation around backwards.
    Low value is DD-2w and High Value is DD.
    Works the same as a timeline with the lowest value to the left and high to the right.

    So it should be -
    Where ’Finish’ is within range of ’DD-2W’ and ’DD’
    And you don’t even need the activity complete status

    Works a treat for me

    Andy
  2. 0
    Morne Beeslaar ·
    Cheers Andy,

    Works a treat!