Hide Budgeted Cost after updating Activity %
In the Open Standard
Irfan KhanMember for 17 years 3 months
- Created
- 2
- 2
0
Hi to all,
I assigned my cost throught Resource = Material to each & all activity.
But when i m going to update my activity (Activity % Complete)after having percentage of activity my cost is not showing from Budgeted Total cost coloumn.
pls reply any1
thanks...........;)
I assigned my cost throught Resource = Material to each & all activity.
But when i m going to update my activity (Activity % Complete)after having percentage of activity my cost is not showing from Budgeted Total cost coloumn.
pls reply any1
thanks...........;)
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?