Resource limit issue between users
In the Open Standard
David BladesMember for 22 years 6 months
- Created
- 3
- 6
0
I have 4 users using P6.2. In resources we have set some limits the max units/time column.... operator 2, water tank 8.
When I log on I can see these limits ok and I can see the limits set by other users on other resources. The problem is the other users are not seeing the limits set by me. I have checked users access and all seems OK. Is there perhaps a security profile I am missing??
Grateful for any help??
Thank you in advance
David
When I log on I can see these limits ok and I can see the limits set by other users on other resources. The problem is the other users are not seeing the limits set by me. I have checked users access and all seems OK. Is there perhaps a security profile I am missing??
Grateful for any help??
Thank you in advance
David
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?