Start and Finish FLOAT

Ali FarhatMember for 18 years
Created
5
39
0
What is the difference between Start Float and Finish Float?
Start Float = Late Start - Early Start
Finish Float = Late Finish - Early Finish

5 replies

Oldest first
  1. 0
    Shah. HB ·
    Hi Ali

    Both yields same result but the way of computing is different
  2. 0
    Rodel Marasigan ·
    Ali,
    One is calculated by Forward Pass and the other is calculated using Backward Pass.
  3. 0
    Vladimir Liberzon ·
    Both are calculated using Forward and Backward passes but still may be different.
  4. 0
    Ali Farhat ·
    So what is the use of the option in Scheduling dialog box that allows you to choose betwee start float, finish float, or the smallest between them?
  5. 0
    Vladimir Liberzon ·
    Start Float shows the delay of sctivity start that does not delay project finish if everything will be done as expected.
    Finish float shows the delay of activity finish that does not delay project finish if everything will be done as expected.

    Actually it is more interesting to understand the delay of activity finish that will not delay project finish if current activity will be done slower than expected (we call it super float).

    I think that start float is most useful because you decide when to start each activity. When start is known finish is defined.

Log in or join to reply