Progress payments

Andreas SchröderMember for 16 years 3 months
Created
4
2
0
Hi everyone,

Is there a possibility to enter progress payments into a primavera schedule? (Could be time or Work progress)
A friend told me about a solution with payment-milestones. Actually i don’t like this solution, so i would be very delighted about any other Ideas/Comments.

Regards

Andreas

4 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Anreas,
    I normally used LOE with calendar define for progress payment. That should give you a good cash flow forecast and able to enter payment in time or work progress.
  2. 0
    Andreas Schröder ·
    Hi Rodel,

    thanks for your advice.
    I am sorry but is it possibile that you go a little bit more into detail. How do if Define Payments via the Calendar using LOE?

    Many Thanks for your advice in advance

    regards

    Andreas
  3. 0
    Rodel Marasigan ·
    Andreas,
    Define a calendar with Progress period as working only and the rest are non-working (i.e. every end of the month or every fortnight) then assign to LOE activity.
  4. 0
    Emorider None ·

    Dear Rodel, Can you explain

    Dear Rodel, Can you explain "how do you load progress payments" after creating an LOE acitivity with suitable calender?How can you create budgeted and actual cash flow with this LOE?

    Thank you in advance

Log in or join to reply