Draft Program

Arun VasanthMember for 17 years
Created
6
2
0
Dear Friends

I have made a draft program of a tower.

Who ever needs the copy send me the email IDS .
Please make ur comments.
My concern is hw to reduce the total float in the program????


With regards
Arun.V

6 replies

Oldest first
  1. 0
    Ronald Romero ·

    Hi Arun,

    Send me the pogram.

    You can reduce float by

    1. linking it properly.
    2. Defining contractual milestone where you can link series of activities and acts as interim dates for computing total float.
    3. resource it properly and leveling the resource.

    regards,

    Ronald
  2. 0
    Samer Zawaydeh ·
    Dear Arun,

    Look at the critical activities and try to increase the resources to reduce the duration.

    With kind regards,

    Samer
  3. 0
    Ronald Romero ·
    Samer,

    What you mean is incresing the duraion by reducing resouces for the critical path.

    regards,
  4. 0
    Samer Zawaydeh ·
    Dear Ronald,

    You are correct, if we are talking about Total Float issue, then he might have something wrong with sequencing and linking of activities. I was referring to reducing the total time of the project.

    With kind regards,

    Samer
  5. 0
    Arun Vasanth ·
    Send me the Email IDS

    Regards
    Arun
  6. 0
    Ronald Romero ·
    Arun,

    My email is ronnieksa@yahoo.com.

Log in or join to reply