Design Programme
In the Open Standard
Sunil KumarMember for 21 years
- Created
- 13
- 5
0
Has anybody done deliverable schedule with resource assignment, if so can anybody please share some knowledge on that, because i have to do that for a particular project & i am struck as i couldnt able to proceed further.
As i have got around 500 deliverables with each deliverable having 3-4 sub activities like issued for comment, isssued for apporval & Approved for construction, how to structure this programme and also how to assign resources & cost for this ( my resource being manpower & Cad personals).
Plz suggest...
Sunil
As i have got around 500 deliverables with each deliverable having 3-4 sub activities like issued for comment, isssued for apporval & Approved for construction, how to structure this programme and also how to assign resources & cost for this ( my resource being manpower & Cad personals).
Plz suggest...
Sunil
13 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?