Total Float
In the Open Standard
AV
Arun VasanthMember for 17 years 1 month
- Created
- 13
- 14
0
13 replies
Oldest first- 0SDStephen Devaux ·Hi, Arun.
I’d approach it by identifying which critical tasks have the most drag. Then I’d compress the schedule by shortening them up, splitting them, or fast tracking them (SS relationships) wherever I could without damaging the project by increasing risk, etc.
Then if the critical path has changed, I’d check which activities now have the most drag, and I’d keep repeating this process until most of the float was gone and I had a shorter (and often more profitable!) schedule. If it’s shorter but not more profitable, I’d see if a shorter project has value for the customer, and, if it does, negotiate an early delivery incentive.
Unfortunately, Primavera (unlike Spider or MSP with an add-on) doesn’t compute drag, so you’ll have to do the drag calculation "manually".
Good luck.
Fraternally in project management,
Steve the Bajan - 0IZIzam Zakaria ·
Arun,
To have better schedule, we should have better links or sequence(not depend on software itself) Of course every single activity shall have next activity. Otherwise U will have big gap in between early and late curves.
I wish I can help u but I dun know what kind of industry u involved. U have to know what is critical items on ur schedule and the best way is ask project team about the sequence. That is what I did thus far, but if the activity confirmed wont have succescor then link FF+++ with last completion activity.
Cheers - 0SHShah. HB ·Hi Mike
Assume a floor in building construction projects where the last activity is tied to an activity named as floor completion(Dummy 1) and that floor completion is tied to respective sectional completion and finally sectional completion is tied to project handover
Please be noted that i might be wrong but i proposed to get the correct logic through discussion in this forum
.-Intermediate dummy activity