s curve

Kumar SMember for 16 years 8 months
Created
1
2
0
Dear Guys,

A simple question.

how can we define the S curve.
what is the standard defination..

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Kumar,
    The S Curve is a well known project management tool. The name derives from the S-like shape of the curve, flatter at the beginning and end and steeper in the middle, because this is the way most of the projects look like. It is a display of cumulative vlaue (costs, labour hours or other quantities) plotted against time.

Log in or join to reply