Skip to content

Budgeted Cost not Showing.....

Irfan KhanMember for 17 years 3 months
Created
1
2
0
I m working on cost loaded schedule but I loaded cost manually i.e. I created one resource (material) and assigned to all activities & fill the cost in front of activities i.e. In the budgeted cost column.
After assigning cost to all activities I got correct my Total Budgeted Cost.

But whenever I am going to update my schedule by Percentage the cost is decreasing.

Why this is happening please help………!

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Irfan,
    If cost is manually input you need to un-tick calculate cost from unit on each assigned resource(Activity Window-> Resource tab-> right click then select customize Resources columns and under general select or double click calculate cost from units) otherwise if resource have no rate it will be back to zero.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?