Budgeted Cost not Showing.....
In the Open Standard
Irfan KhanMember for 17 years 3 months
- Created
- 1
- 2
0
I m working on cost loaded schedule but I loaded cost manually i.e. I created one resource (material) and assigned to all activities & fill the cost in front of activities i.e. In the budgeted cost column.
After assigning cost to all activities I got correct my Total Budgeted Cost.
But whenever I am going to update my schedule by Percentage the cost is decreasing.
Why this is happening please help………!
After assigning cost to all activities I got correct my Total Budgeted Cost.
But whenever I am going to update my schedule by Percentage the cost is decreasing.
Why this is happening please help………!