Re-basline with progress......L of E error
In the Open Standard
Oliver MellingMember for 19 years 5 months
- Created
- 8
- 5
0
I have a project were the PM has agreement to draw the line in the sand as the current programme stands.
i.e. current programme becomes the new baseline.
The problem is that after saving the current programme as a baseline, any activities with progress (that are not exactly on target) show different baseline dates to the current programme.
When detached the new baseline has the same current dates as the current programme, but its baseline dates are different (on activites that have progressed but are not on target).
Can anyone explain why this is?
i.e. current programme becomes the new baseline.
The problem is that after saving the current programme as a baseline, any activities with progress (that are not exactly on target) show different baseline dates to the current programme.
When detached the new baseline has the same current dates as the current programme, but its baseline dates are different (on activites that have progressed but are not on target).
Can anyone explain why this is?
8 replies
Oldest firstLog in or join to reply