Store Period Performance

Rifky SoedirdjaMember for 16 years 5 months
Created
3
2
0
Another question about how to use Store Period Performance.

For example, I have 1 activity, let’s say Activity A, with budgeted labor Units = 100 Mhrs. Progress for this week = 50%, so Actual Labor units = 50 Mhrs and I run the Store Period Performance based on Financial Period for this week.

The following week, we achieve another 20% progress, means actual Labor units for that period is 20 mhrs. So, total Cumulative Actual Labor Units = 70 mhrs.

But in Activity Usage Spreadsheet, the distribution of Actual Labor Units is not 50 mhrs & 20 mhrs. It shows 32 mhrs & 38 mhrs. Total manhours is still the same 70 mhrs.

So, how to freeze the Actual labor units from the previous week (50 mhrs + 20 mhrs, instead of 32 mhrs + 38 mhrs)actually? Did I make a mistake when I apply Store Period Performance? Can somebody guide me the steps?

Your help is appreciated. Thanks.

Rgds,

Rifky

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Rifky,
    Don’t use Actual Labor unit field from Units and use Financial Period Value instead on your spreadsheet. That is where all the data stored (i.e. Period Actual Labor Unit, etc…). Using original data will proportion from actual start to data date.
  2. 0
    Rifky Soedirdja ·
    Thanks Rodel.
    Is it possible to show % complete for that Period also besides the Units, Cost, etc?

    Rgds,

    Rifky
  3. 0
    Rodel Marasigan ·
    Rifky,
    Unfortunately not both at the same time. You can either show % complete or Units and Cost.
    Percent complete can be showed using Spreadsheet Options-> Calculate Average then enter the total cost or unit over 100.
    For Planned use Period Planned Value Cost or Unit and for Actual use Period Earned Value Cost or Unit.