Activity Dates does not reflect it’s duration

Regina LucenaMember for 16 years 2 months
Created
5
2
0
Had any of you ever have this problem? Please let me know how to solve it in P6 if any idea...or happen to you once..
Thanks a lot!!

5 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Hi Regina,
    What do you mean by Activity dates does not reflect its duration? Is it on Gantt chart or on Column? Can you elaborate more so I can help you out?

    Anyway here is my attempt.
    If not showing on the Gantt chart the possible reasons are:
    1) Bar duration is too small to show on Timescale (Change the time scale (i.e. Month/week or week/day).
    2) Original Duration is not synchronize with remaining duration (i.e. OD =5 RD = 0) To resolve that under Project Window-> Calculation tab-> Under Activities , Link Budget At Completion for not stated activities is not tick. It also combines with Reset remaining duration and Unit to original.
    3) Calendar problem -> check your calendar settings.

    If not showing on the column:
    See 2 or 3 suggestion above.
  2. 0
    Regina Lucena ·
    Rodel what I mean is when you substract finish date and start date the result number of days do no reflect the duration of the activity. It is not a format problem, so answer #1 does not apply.

    I will check your answers 2 & 3 tomorrow and let you know tomorrow evening....thanks a lot for your prompt support!
    Regina
  3. 0
    Anoon Iimos ·
    Regina,

    Check your time period settings
  4. 0
    Rodel Marasigan ·
    Regina,
    If total duration it’s Hours per time period settings. It should match to your calendar. If using P6.1 to P6.2 check Edit-> User Preferences-> Time Units tab and under Hours per time period change working hours to match your calendar (i.e. 8/d, 40/w, 173/m, etc...). If using P6v7 check Admin-> Admin Preferences-> Time Period tab-> make sure use calendar to hour per time period is tick and under calendar settings click time period and change from there.
  5. 0
    Andrew Dick ·
    Also check what dates are used to drive the bar itself.
    Maybe have an old baseline assigned that drives the dates or bar set to another set of dates.
    Long shot but who knows.

    Andy